Siyrbay Copper Deposit
Siyrbay Copper Deposit
•Bayanaul District, Pavlodar Region
•190 km from Pavlodar
•40 km from Bayanaul
•195 km from Karaganda
•Paved Pavlodar-Bayanaul highway
•40 km to the nearest railway station (Shoptykol)
•Power transmission line located 13 km from the licence area (Zhanazhol village)
•Nearest mining operations: Maikuben coal mine – 30 km Maikain Mine – 70 km
Exploration History
•1966 – 1968
Eight trenches were excavated and one 72 m inclined drillhole was completed. The exploration programme intersected copper mineralization.
•1989 – 1991
Three vertical drillholes, ranging from 210 m to 310 m in depth, were completed. Two main trenches (Nos. 10 and 11) were excavated, with a combined excavation volume of 2,040 m³.
Trench No. 10 intersected a mineralized interval grading 0.26-0.53% Cu. Drillhole No. 1003 intersected copper mineralization grading 0.45% Cu.
• The deposit has forecast copper resources of approximately 300,000 tons of contained copper, at an average grade of 0.5% Cu.
•2005 – 2008
Four inclined drillholes, ranging from 275 m to 317 m in depth, were completed.
Drillhole S-1 intersected: 0-52 m (oxidation zone): 0.24% Cu; 123-125 m: 0.23% Pb, 0.24% Zn and 0.05 g/t Au.
•2019 – 2025
Four inclined drillholes (1,200 m) were completed. Thirteen trenches were excavated, with a total excavation volume of 2,038 m³.